Fitting the Demolition Hammer (see figures D−H)
Only carry out the assembly on an even, horizontal surface. Remove the carrying handle of the demolition hammer before assembly. Please refer to the operating instructions for the demolition hammer.
Image D:
- Set the lowest working angle see Setting the Working Angle on the trolley.
- Place the bottom end of the trolley frame on a stable surface of the appropriate height, so that the surface area for the demolition hammer is aligned horizontally.
Images E−F:
- Place a handle receptacle fastening block (8) on the uppermost frame slot of the trolley.
- Place a tool holder fastening block (9) on the bottom-most frame slot of the trolley. Turn the fastening block as shown in figure F, in a way that's appropriate for the demolition hammer that's meant to be used.
- Put one threaded rod (13) each through the ends of the fastening blocks. The tabs of the threaded rods must point outwards.
- Put one washer and one lock nut each – from the demolition hammer fastening set (14) – onto the bottom end of the threaded rods. Loosely tighten the lock nuts with an open-ended spanner of 17 mm.
Image G:
- Place the demolition hammer on the fastening blocks so that the coil spring damping of the demolition hammer is in the recess of the tool holder fastening block (9). Ensure that the lock bolt and the retaining bracket on the tool holder of the demolition hammer remain accessible when the tool is changed later.
GSH 16-28: Open the retaining bracket.
Image H:
- Place the second handle receptacle fastening block (8) on the top threaded rods, and the second tool holder fastening block (9) on the bottom threaded rods (at the same orientation as the bottom tool holder fastening block (9)). Push both blocks onto the demolition hammer as far as they will go.
- Place the top panel (10) onto the threaded rods with the recess over the tool holder.
- Tighten the locking nuts on the bottom end of the threaded rod with an open-ended spanner of 17 mm.
- Put one washer and one spring lock washer each – from the demolition hammer fastening set (14) – onto the top end of every threaded rod.
- Put one star grip nut each – from the demolition hammer fastening set (14) – on every threaded rod and tighten it well.
Hang the cable of the demolition hammer in the cable suspension (6) at the handle.
Read and observe the demolition hammer operating instructions for the assembly of the application tool in the demolition hammer.
GSH 16-28: Pivot the tool retainer of the tool holder as far as it will go at the tool holder fastening block (9) to lock the application tool in place.